lans
to build a pedestrian bridge over the Missouri River between
Nebraska and Iowa has caused much controversy over the past few
years. In 2000, former Senator Bob Kerrey obtained $19 million in
federal funding to start the project. At that time, both Nebraska
and Iowa agreed to add an additional $1.5 million each and the Papio-Missouri River Natural Resources District added another $1
million to the pot.
The entire project was to cost no more
than $23 million but when bids were received in 2004, the lowest
was $22 million over budget, doubling the expected cost. FIGG
Engineering Company of Tallahassee, FL. was hired by the Fahey
administration to design
 |
 |
Artist conceptual drawing of the Pedestrian Bridge designed
by Figg Engineering. |
 |
a bridge that would be a focal point for the riverfront. The
twin-spire design they submitted included long sweeping curves and
majestic twin sails.FIGG and Omaha city officials had been
trying to come up with a more scaled-back design over the past 18
months that could go back out to bid but the city feared
construction costs would still out-weigh their budget. The Fahey
administration has since decided to terminate its agreement with
FIGG and seek out a design-build contractor without going through
the normal bidding procedure. Design-build is a system in which
one contractor performs both the architecture/engineering and the
actual construction. Several teams have expressed interest
including Hawkins Construction Company of Omaha who would team
with FIGG and HDR, acting as both designer and general contractor. Others
include Jensen Construction
Co. of Des Moines, APAC-Kansas Inc. of
Overland Park, KS., Flatiron Construction of Longmont,
CO.,
Hardesty & Hanover of Annapolis, MD. and Christensen Bros.
Inc. of Cherokee, IA.. Although FIGG has already been paid $3
million for the work they put into the design, not all of that
money will go to waste. Any firm picked for the project will
receive all of the environmental and pre-construction reports. The
chief concern for those who are advocates for building the bridge
is that cost is the overriding consideration with quality second.
The formal request does state, however, that this will need to be
an architecturally significant landmark. Formal requests
for proposals will be out sometime this month or next. Interested
companies will need to submit their proposals within four to six
weeks then a committee will select the design and construction
company. Officials believe the design-build concept should allow
for quicker construction with work possibly starting by next
summer.
|